Arequipa Building Projects
The Garman Missionary training center in nearing completion. Extreme will complete the two dormitory rooms for missionary and pastor trainees by mudding, painting, installing electrical fixtures, installing carpet and trim, installing doors, and construct beds and tables.
The second story brick walls of the church are being constructed and the roof will be installed soon. Extreme will be installing electrical wiring and fixtures, paint, tile, carpet, bathroom fixtures, acoustical tile, and room dividers.
The Garman Training Center and Daniel Walker District Center continues to get closer to completion. Besides the work that was done during Extreme Peru: Arequipa 0 and Extreme Peru: Arequipa 1, here is how the progress has continued.
Update as of September 5, 2009- Windows have been installed in the downstairs
- All tile is down and grouted
- All trusses have been installed
- Both downstairs bathrooms have been completed and are fully functional
- Exterior stairs have been assembled, and are fully functional.
|